Contractor Performance Analysis Report
- ohussein31
- Oct 8
- 3 min read
Updated: Oct 16
Executive Summary
This report presents a focused performance analysis of project contractors. Based on 20 completed projects, the goal is to determine the most reliable contractor. Project-level data was analyzed to assess cost variance, schedule adherence, safety incidents, quality scores, and earned value indices (CPI/SPI).
Problem Statement
Your organization engages multiple contractors across several regions to deliver complex infrastructure projects. While portfolio-wide performance shows overall cost efficiency, contractor and regional variability introduce execution risks. This analysis aims to answer:
Which contractor provides the most consistent and effective project delivery?
Addressing this questions supports better procurement decisions, risk management, and operational planning.
Key Findings
This Table below summarizes the performance of Contractor A and Contractor B across cost, schedule, safety, and quality dimensions. Both contractors demonstrate stable overall performance, with Contractor B leading slightly in cost and schedule efficiency.
Metric | Contractor A | Contractor B | Commentary |
Projects | 12 | 8 | Both actively engaged; staggered execution |
SPI | 0.92 | 1.03 | A slightly behind schedule; B ahead |
CPI | 1.00 | 1.01 | Both on/under budget; B more efficient |
Incident Rate / Incidents | 26.08 % (134) | 17.18 % (88) | B shows stronger safety culture |
Quality Score | 79 | 79 | Comparable quality outcomes |
Performance Grade | B | B | Consistent across contractors |
Contractor B is currently the stronger performer, delivering ahead of schedule (SPI 1.03) and under budget (CPI 1.01) while maintaining a lower incident rate of 17.18 per 1 000 hours and a quality score of 79. Contractor A remains on budget (CPI 1.00) but is behind schedule (SPI 0.92) and shows a higher incident rate of 26.08 per 1 000 hours. Overall, the program is financially stable, with Contractor B setting the benchmark for cost, safety, and schedule performance, while Contractor A requires closer attention to safety management and schedule recovery.
Future Outlook & Recommendations
Allocate Additional Work to Contractor B Contractor B has demonstrated consistent reliability — ahead of schedule, under budget, and maintaining safety and quality performance. Allocating a greater share of upcoming work or complex scopes to Contractor B could enhance overall program efficiency and mitigate schedule risk.
Implement Schedule Recovery Plans for Contractor A With an SPI of 0.92, Contractor A requires targeted recovery measures. Focus areas should include improved resource planning, tighter schedule monitoring, and milestone-based tracking to address cumulative delays before they impact the program end date.
Strengthen Safety Oversight for Contractor A
The higher incident rate (26.08 per 1 000 hours) indicates a need for additional field safety supervision, enhanced hazard awareness training, and joint safety audits with Contractor B to share best practices.
Maintain Quality Benchmarks
Both contractors achieved a quality score of 79, but continued auditing and feedback loops will help sustain or improve workmanship as project complexity increases.
Expand Performance-Based Incentives
Introduce incentives linked to SPI > 1.0 and CPI ≥ 1.0 to reward schedule and cost discipline, encouraging both contractors to sustain efficiency gains.
Leverage Contractor B as a Performance Model
Use Contractor B’s planning and execution approach as a benchmark. Facilitate cross-contractor collaboration sessions where B shares effective schedule and safety management strategies with A’s project teams.
Summary of Insights
This analysis confirms that Contractor B currently delivers the strongest overall performance, achieving higher cost and schedule efficiency while maintaining solid safety and quality outcomes. Contractor A, while performing adequately in cost and quality, faces challenges in schedule adherence and safety management.
By reallocating future workloads toward high-performing contractors, enforcing targeted schedule recovery plans, and strengthening cross-contractor learning, the organization can enhance delivery consistency and reduce risk exposure. Sustained performance monitoring and incentive-based frameworks will ensure that these improvements translate into long-term operational excellence across all regions.